June 19, 2015 
 
Subject: 2015 MFT Street Rehabilitation Project - Notifications 
 
Dear Resident: 
 
Again this year, the City will undertake an annual project aimed at maintaining current infrastructure and 
roadways within the community. The City of St. Charles is pleased to inform you that the street adjacent 
to your home or property has been included for resurfacing this year.   
 
2015 STREET PROGRAM PROJECT LOCATIONS: 
 
CONTRACTOR: 
The contract for this work has been awarded to Schroeder Asphalt Services, Inc. of Huntley, IL. as the 
general contractor for this year’s program. 
 
START DATES: 
The contractor will not be working on all streets at one time, but will be splitting the work  up in the 
community by West and East Side Streets.  All start dates are weather pending. 
 
  West Side Streets:  The construction is tentatively scheduled to begin on June 29
th
. 
  East Side Streets:  The construction is tentatively scheduled to begin on July 13
th
.  
  North Tyler Road:  This project location will include complete replacement of the watermain.  
The work is tentatively scheduled to begin on August 1
st
, pending approval of the IEPA permit.