HTML Preview Bridge Construction Project Report page number 1.


BRIDGE REPLACEMENT OR NEW BRIDGE CONSTRUCTION
PROJECT PROGRESS REPORT
Des. No.: Structure No.:
ITEM ITEM VALUE PERCENT
PERCENT Last Report This Report COMPLETE
Process Survey 2.0
Design Preliminary Grade 1.0
Hydraulic Analysis 5.0
Prepare Preliminary Title Sheet & Index Sheet 0.5
Prepare Prelim. Typical Cross Section 1.0
HYDRAULICS SUBMITTA
L
9.5 0.0
Design Grade 1.0
Design Prel. Structure Geometrics 1.5
Prepare Prel. Channel Layout 1.0
Economic Cost Analysis (Structure Type) 3.0
Preliminary Guardrail Design 1.5
Preliminary R/W Design 1.0
Preliminary Drainage Design 1.5
Preliminary Quantities & Cost Estimate 1.5
Preliminary Plan & Profile Sheet 1.0
Prepare Prel. Layout Sheet 1.0
Prepare Preliminary General Plan Sheet 1.0
Preliminary Cross Section Sheets 0.5
STAGE 1 REVIEW SUBMISSION 25.0 0.0
Revise plans per Stage 1 Review 1.0
Determine Required Pile Capacities 2.0
GEOTECHNICAL INVESTIGATION
REQUEST SUBMITTA
L
28.0 0.0
Clear Zone / Roadside Safety Design 1.5
Prelim. Approach, Drive & Intersection Details 1.5
Prelim. Plat #1 or #3 0.5
Preliminary Maintenance of Traffic 2.0
Detail Sheets 0.5
Road Summary Sheet 0.5
Prel. Plot of Final Cross Sections 0.5
PRELIMINARY FIELD CHECK PLAN
S
35.0 0.0
Field Inspection 1.5
Revise Plans per Field Check Comments 1.0
Final R/W Design & Plans 1.5
Final R/W Plat #1 or #3 0.5
PRELIMINARY R/W PLANS SUBMITTA
L
39.5 0.0
Foundation Selection 0.5
Construction Cost Estimate Update 1.0
Final Approach, Drive & Intersection Details 1.0
Finalize Title Sheet for R/W Plans 0.5
Finalize Typical Cross Sections 1.0
Final Plan & Profile Sheets 2.5
Soil Boring Sheet 0.5
Preliminary Approach Table 1.0
Final Cross Sections 2.5
STAGE 2 REVIEW SUBMISSION 50.0 0.0
STATUS REPORT