VALIDATION MASTER PLAN FOR VALUE PLASTICS FACILITY MOVE  
ANY COPY MADE FROM THE ELECTRONIC VERSION SHALL BE CONSIDERED AN UNCONTROLLED COPY. INDIVIDUALS WITH UNCONTROLLED COPIES ARE RESPONSIBLE FOR ENSURING THE USE OF THE CURRENT 
VERSION. REVISION LEVELS ARE ELECTRONICALLY CONTROLLED. 
 
 
PRINTED HARDCOPIES ARE FOR REFERENCE USE ONLY 
1.0  PURPOSE 
1.1  The purpose of this Validation Master Plan (VMP) is to identify the validation and testing 
requirements necessary to qualify the products manufactured by Value Plastics dba Nordson 
MEDICAL after relocation from 3325 South Timberline Road, Ft. Collins, CO 80525 to 805 West 
71
st
 Street, Loveland, CO 80538.     
1.2  There will be no changes to the Quality System, materials, ERP system, tools, equipment, 
manufacturing processes and quality inspections as a result of this facility move.  In addition the 
people who have been doing the work in the current plant will be the same people doing the 
work in the new plant. 
2.0  POLICY COMPLIANCE 
This Plan complies with corporate policy requirements for validation as stated in the Validation 
Master Plan IFS document VMP7.1 and ISO 9001 and ISO 13485 requirements 
3.0  REVIEWERS, APPROVERS AND EXECUTERS 
Reviewers, approvers and executers of this plan are captured in the approval routing tab of this 
document in IFS. 
4.0  SCOPE OF VALIDATION 
NOTE:  All products manufactured by Value Plastics are proprietary to Value Plastics; the majority 
of the machines, molds and equipment are owned by the company.   There is not a 1:1 correlation 
with mold and machine for building individual parts (i.e, parts can be built on any number of 
machines using a number of different molds).  With over 4200 molded parts that can be run in 
multiple different machines and molds, it would require over 180,000 individual validations to 
verify every possible combination of part and mold to machine.  This would result in 
approximately 1.42M validation hours.  It is not feasible to validate each part in each 
configuration.  Therefore we will approach this facility move validation in a staged manner. We 
will validate every piece of critical manufacturing equipment using a representative mold and part  
and will allow our standard quality inspection processes to verify that parts produced post-facility 
move continue to meet specification.  (Note that we will
 conduct a validation for any dedicated 
molds/machines.) 
 
This Master Validation Plan addresses all activities related to equipment, utilities, processes, and 
systems that may impact product quality post facility move.  Specific systems, equipment, 
infrastructure and procedures to be qualified and processes to be validated were determined based 
on our standard Validation Master Plan (VMP7.1) and associated work instructions.  
4.1  In-Scope 
4.1.1  Injection Molding Machines moved to new facility 
4.1.2  Injection Molding Machine monitoring software 
4.1.3  Injection Mold Tooling moved to new facility