HTML Preview Construction Progress Report page number 1.


NUMBER
WEEKLY CONSTRUCTION PROGRESS REPORT
North Dakota Department of Transportation, Construction Services
SFN 10200 (Rev. 03-2015)
Contractor
Week Ending
Project
Type Of Work
County
Work Completed
Contract Amount
WORKING DAY CONTRACT
COMPLETION DATE CONTRACT
Allowable working days:
Contract completion date:
Time charge started:
Calendar days from start to completion date:
Working days charged this week:
Calendar days expired:
Percent Time:
- WITH GUARANTEED MIN. NO. OF WORKING DAYS -
Working days charged to date:
Percent of time expired:
Guaranteed number of working days:
Time charge started:
Working days charged this week:
Working days charged to date:
Portion of Structure
or Location of Work
Percent of
Contract
Items of Work
Remarks:
MBE Remarks:
S
T
W
F
S
Working days charged this week:
Actual days worked this week:
The contractor will be allowed seven calendar days after the last day of the week covered by this report to file a written protest
if he disagrees with the time charges. (See Spec. 108.06 A.2)
Received By (Contractor)
Date
Construction Office
District Office
Contractor
File
Submitted By (Project Engineer)
T
M
DOWNLOAD HERE


All paid jobs absorb and degrade the mind. | Aristotle