HTML Preview Construction Work Schedule page number 1.


FAIRFAX COUNTY DEPARTMENT OF PUBLIC WORKS AND ENVIRONMENTAL SERVICES
DEVELOPMENT CONSTRUCTION SCHEDULE
MONTHS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
** **
1. CONSTRUCTION OF BUILDINGS
2. DURATION OF SILTATION
CONTROLS
3. CLEAR & ROUGH GRADE
4. INSTALL SANITARY SEWER
5. INSTALL STORM DRAINAGE
6. INSTALL UTILITIES
7. INSTALL BASE ASPHALT, C & G,
and SIDEWALK
8. INSTALL FINAL PAVING
9. FINAL GRADING, SEEDING, OR
SODDING
10. EXPECTED TIME TO BOND
RELEASE
PLAN NAME: PLAN #:
DATE PREPARED: BY:
Signature of person preparing schedule
**Note: Effective July 1, 1995, the period of performance granted for Agreements with a Public Improvement Value of less than $750,000 (prior to addition of damage, supervision & administration and inflation
factors) not to exceed 24 months and a Public Improvement Value of $750,000 and greater not to exceed 36 months.
OSDS#30, revised 4/99